CAPTION
Requesting approval of Change Order No.1 to Construction Contract No. HCDD1-13-022-04-29B Pct. 2 "FM 495 DRAIN-WISCONSIN ROAD FIELD CROSSING" with Rojas Heavy Equipment, LLC dba Rojas Construction & Paving an increase in the amount of $40,817.22.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 12/30/2014 02:00 PM |
| Final Approval | Monica Salinas | 01/02/2015 05:05 PM |
- Form Started By:
- Jaime Salazar
- Started On:
- 12/30/2014 01:09 PM
- Final Approval Date:
- 01/02/2015