AI - 48663
7.
DRAINAGE DISTRICT
- Meeting Date:
- 03/03/2015
- Submitted By:
- Jaime Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
A.) Requesting approval to advertise for RFQ No. HCDD1-15-004-04-01 "Real Estate Appraisal Services - Pool".
B.) Requesting approval of "Pool" of pre-qualified firms submitting Statements of Qualifications for ranking on an "As Needed Basis" per project by the Hidalgo County Drainage District No. 1 for projects that require said services as set forth in the requirements stated in RFQ No. HCDD1-15-001-02-18 "PROFESSIONAL ENGINEERING SERVICES-POOL".
C.) Discussion, consideration and possible action for AGUA Special Utitlity District to use Hidalgo County Drainage District No. 1 ditch system to run a force main.
2013 BOND SERIES
D.) Requesting approval of Change Order No. 1 with Foremost Paving, Inc. for Construction Contract No. HCDD1-14-003-02-11 "Pct. 4 West Main Drain Existing Weir Modification & Existing Concrete Slide Gate Control Structure Improvements". Extension of Contract time due to manufactures delay in material delivery. No amount associated with Change Order No.1
E.) Requesting approval to accept bid and approval to award Construction Contract to lowest bidder meeting all specified requirements for RFB No.HCDD1-13-024-09-26A "Drainage Improvements Project East Donna Drain-Flood Pump". SANCO General Contracting, Inc. in the amount of $845,824.66.
F.) Requesting approval to accept bid and approval to award Construction Contract to lowest bidder meeting all specified requirements for RFB No. HCDD1-13-026-09-26C "Drainage Improvements Project South Mercedes Drain - Flood Pump". SANCO General Contracting, Inc. in the amount of $665,343.48.
B.) Requesting approval of "Pool" of pre-qualified firms submitting Statements of Qualifications for ranking on an "As Needed Basis" per project by the Hidalgo County Drainage District No. 1 for projects that require said services as set forth in the requirements stated in RFQ No. HCDD1-15-001-02-18 "PROFESSIONAL ENGINEERING SERVICES-POOL".
C.) Discussion, consideration and possible action for AGUA Special Utitlity District to use Hidalgo County Drainage District No. 1 ditch system to run a force main.
2013 BOND SERIES
D.) Requesting approval of Change Order No. 1 with Foremost Paving, Inc. for Construction Contract No. HCDD1-14-003-02-11 "Pct. 4 West Main Drain Existing Weir Modification & Existing Concrete Slide Gate Control Structure Improvements". Extension of Contract time due to manufactures delay in material delivery. No amount associated with Change Order No.1
E.) Requesting approval to accept bid and approval to award Construction Contract to lowest bidder meeting all specified requirements for RFB No.HCDD1-13-024-09-26A "Drainage Improvements Project East Donna Drain-Flood Pump". SANCO General Contracting, Inc. in the amount of $845,824.66.
F.) Requesting approval to accept bid and approval to award Construction Contract to lowest bidder meeting all specified requirements for RFB No. HCDD1-13-026-09-26C "Drainage Improvements Project South Mercedes Drain - Flood Pump". SANCO General Contracting, Inc. in the amount of $665,343.48.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 02/27/2015 09:21 AM |
| Final Approval | Monica Salinas | 02/27/2015 05:46 PM |
- Form Started By:
- Jaime Salazar
- Started On:
- 02/25/2015 05:10 PM
- Final Approval Date:
- 02/27/2015