CAPTION

Acceptance and approval of Change Order No. 8 for additional 19 days due to rain days and dry out days for the months of June and early July, Contract No. C-14-067-06-03 with JCon Construction, LLC as reviewed/approved by project architect of record, Mata-Garcia Architects, LLP for: Hidalgo County Precinct No. 4 -"Construction of the Linn-San Manuel Emergency Services Facilities" with authority for County Judge, or Court Member to execute document.

BACKGROUND

The new projected Substantial completion as per Change Order No. 8 is:  July 24, 2015 

Fiscal Impact

FISCAL YEAR:
2015
ACCT. #:
5-1301-419-40-124-136-0-730
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

PO#712761
Change order has no fiscal impact.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 07/14/2015 03:05 PM
Budget and Management Veronica Ortiz 07/15/2015 09:50 AM
Auditor's Office Monica Salinas 07/17/2015 05:42 PM
Form Started By:
moysalazar
Started On:
07/14/2015 10:33 AM
Final Approval Date:
07/17/2015