CAPTION

Change Order No. 1 for Construction Contract: HCDD1-14-032-12-17 Main Floodwater Channel Weir No. 5-Slope Repair recommended by Project Engineer, reviewed and signed by District General Manager for a decrease in the amount of $42,230.20 and Increase of 210 construction days.  

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Budget and Management Veronica Ortiz 03/18/2016 03:04 PM
Final Approval Monica Salinas 03/18/2016 04:03 PM