1. Requesting exemption from competitive bidding requirements under the Texas Local Government Code 262.024 (a)(4) for construction management services.
2. Presentation of the scoring grid for the purpose of ranking by Commissioner’s Court of at least three (3) construction management service firms from the county’s approved “pool” as graded and evaluated by Hidalgo County Precinct No. 1, Urban County Program and Hidalgo County Purchasing Department, in connection with and funded through Hidalgo County Urban County Program GLO Contract No. 12-406-0006453/DRS210068 Delta Area Connector/East Lateral project Phases 1, 2 and 3.
3. Authority to negotiate a construction management service contract with the No. 1 ranked firm
for the provision of Construction Management Services for Precinct No. 1 – Delta Area Connector/East Lateral project Phases 1, 2 and 3.
2. Presentation of the scoring grid for the purpose of ranking by Commissioner’s Court of at least three (3) construction management service firms from the county’s approved “pool” as graded and evaluated by Hidalgo County Precinct No. 1, Urban County Program and Hidalgo County Purchasing Department, in connection with and funded through Hidalgo County Urban County Program GLO Contract No. 12-406-0006453/DRS210068 Delta Area Connector/East Lateral project Phases 1, 2 and 3.
| PROFESSIONAL SERVICE FIRM | GRADE | RANKED |
| LeFevre Engineering and Management Consulting, LLC | 97.33% | |
| SAM Engineering and Surveying | 86.67% | |
| Cortran Engineering, PLCC | 86.33% |
for the provision of Construction Management Services for Precinct No. 1 – Delta Area Connector/East Lateral project Phases 1, 2 and 3.
BACKGROUND
Construction Management Services will be conducted at Delta Area Connector/East Lateral project Phases 1, 2 and 3.
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 04/07/2016 04:20 PM |
| Final Approval | Monica Salinas | 04/08/2016 04:57 PM |
- Form Started By:
- sregalado
- Started On:
- 04/07/2016 03:02 PM
- Final Approval Date:
- 04/08/2016