CAPTION

Approval of Payment Application No. 15 in the amount of $178,597.86 submitted by IOC Company LLC, awarded contractor for Precinct 3's "Mile 2 North Roadway Project" as certified for payment by project engineer, L&G Engineer, C-14-153-02-17.

BACKGROUND

$2857.57 funded through PO # 725568

Fiscal Impact

FISCAL YEAR:
2016
ACCT. #:
6-1315-126-20-000-019-0-000
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Funding available as of 8/12/2016.

FISCAL YEAR:
2016
ACCT. #:
6-1315-431-00-123-094-0-721
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Funding available as of 8/12/2016.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 08/12/2016 02:34 PM
Budget and Management Veronica Ortiz 08/12/2016 02:44 PM
Final Approval Monica Salinas 08/12/2016 05:41 PM
Form Started By:
nceballos
Started On:
08/12/2016 10:24 AM
Final Approval Date:
08/12/2016