CAPTION

2013 Bonds
Budget: 330-East Donna Drain
A. Approval of Change Order No. 1 from Mor-Will, LLC in the amount of $$28,000.00 and an additional (10) ten days to Construction Contract No. C-HCDD1-16-040-08-16 Drainage Improvement Project East Donna Drain Flood Pump.

B. Application for Payment No. 2 in the amount of $72,195.75 from Mor-Will, LLC pertaining to Construction Contract No. C-HCDD1-16-040-08-16-Drainage Improvement Project-East Donna Drain Flood Pump.
PO#630511.
Project Engineer: Mark Corbitt, P.E.-Tedsi Infrastructure Group

Budget: 345-Mercedes Lateral

C. Application for Payment No. 2 in the amount of $180, 149.12 from Mor-Will, LLC pertaining to Construction Contract No. C-HCDD1-16-039-08-16 Drainage Improvement Project Mercedes Lateral Flood Pump.
PO#627491
Project Engineer: Mark Corbitt, P.E.-Tedsi Infrastructure Group.

Budget: 365-Rural Drainage Development Pct.4
D. Approval of Change Order No. 2 from Venser Contractors, LLC for an additional 30 days to Construction Contract No. HCDD1-16-045-09-27-Kenyon Rd. & Mile 17 Area Drainage Improvements.

E. Application for Payment No. 2 in the amount of 59,005.61 from Venser Contractors, LLC pertaining to Construction Contract HCDD1-16-045-09-27 Kenyon Rd & Mile 17 Area Drainage Improvements.
PO#630834

BACKGROUND


Fiscal Impact

Attachments

No file(s) attached.

Form Review

Inbox Reviewed By Date
Final Approval Monica Salinas 04/13/2017 04:27 PM
Form Started By:
ccavazos
Started On:
04/13/2017 10:58 AM
Final Approval Date:
04/13/2017