CAPTION
2013 Bonds
Budget 320-Alamo Expressway Drain
A. Request approval of Change Order No. 2 in the amount of $748,715.78 to decrease and zero out construction contract HCDD1-14-008-07-08 Pct.2 Alamo Expressway Drain as per Agenda Item No. 58751 approved by Board on March 07, 2017.
B.Upon approval of Item A, request approval to issue payment for Payment Application No. 8 - Retainage Release to Texas Cordia Construction, LLC in the amount of $8,086.06 pertaining to Construction Contract No. HCDD1-14-008-07-08-Pct.2 Alamo Expressway Drain.
Project Engineer: R. Gutierrez Engineering/ DOS Logistics
Purchase Order: 625452
Budget 320-Alamo Expressway Drain
A. Request approval of Change Order No. 2 in the amount of $748,715.78 to decrease and zero out construction contract HCDD1-14-008-07-08 Pct.2 Alamo Expressway Drain as per Agenda Item No. 58751 approved by Board on March 07, 2017.
B.Upon approval of Item A, request approval to issue payment for Payment Application No. 8 - Retainage Release to Texas Cordia Construction, LLC in the amount of $8,086.06 pertaining to Construction Contract No. HCDD1-14-008-07-08-Pct.2 Alamo Expressway Drain.
Project Engineer: R. Gutierrez Engineering/ DOS Logistics
Purchase Order: 625452
BACKGROUND
Fiscal Impact
Attachments
- AI#58751 BOD 03-07-17
- Tx Cordia Termination Letter -Pct.2 Alamo Expwy Drain.
- AI#60263-Authority for DD1 Engineers to Sign
- TxCordia Pmt#8-Pct.2 Alamo Expwy Dr
- CO#2-Pct.2 Alamo Expwy Dr
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 06/09/2017 05:10 PM |
- Form Started By:
- ccavazos
- Started On:
- 06/08/2017 10:51 AM
- Final Approval Date:
- 06/09/2017