5.
DRAINAGE - CONSENT
Meeting Date:
08/08/2017
Submitted For:
Lora Briones
Submitted By:
Claudette Guerrero, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

2013 Bond Projects
Budget 365-Rural Drainage Development Pct.1

Ratification of the following item:

A. Change Order No. 3 in the amount of $20,117.16 from RDH Site & Concrete, LLC and the addition of four (4) additional days pertaining to Construction Contract No. HCDD1-16-031B-08-09-Mile 6 West & Mile 14 North Area Drainage Imp.  Revised Contract Amount $363,642.16 and Revised Contract Time 123 Days. 