AI - 61246
6.
DRAINAGE - CONSENT
- Meeting Date:
- 08/22/2017
- Submitted By:
- Claudette Guerrero, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
General Fund
Budget: 005-General Fund Administration-Building
Ratification of Change Order No. 1 in the amount of $5,233.00 and the addition of thirty (30) contract days from Metro Electric, Inc. pertaining to Contract No. HCDD1-17-018-05-30 Hidalgo County Drainage District No. 1 Maintenance Building Electrical Upgrade. New Contract Amount $39,423.00 and revised contract time approved 130 days.
Project Engineer: Halff Associates, Inc.
PO#632111
Project Engineer: Halff Associates, Inc.
PO#632111
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 08/18/2017 05:05 PM |
- Form Started By:
- ccavazos
- Started On:
- 08/18/2017 10:28 AM
- Final Approval Date:
- 08/18/2017