6.
DRAINAGE - CONSENT
Meeting Date:
08/22/2017
Submitted By:
Claudette Guerrero, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

General Fund
Budget: 005-General Fund Administration-Building
Ratification of Change Order No. 1 in the amount of $5,233.00 and the addition of thirty (30) contract days from Metro Electric, Inc. pertaining to Contract No. HCDD1-17-018-05-30 Hidalgo County Drainage District No. 1 Maintenance Building Electrical Upgrade.  New Contract Amount $39,423.00 and revised contract time approved 130 days.

Project Engineer: Halff Associates, Inc.
PO#632111

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Monica Salinas 08/18/2017 05:05 PM
Form Started By:
ccavazos
Started On:
08/18/2017 10:28 AM
Final Approval Date:
08/18/2017