AI- 61851
Urban County 12.A.
CC - REGULAR
- Meeting Date:
- 10/03/2017
- Submitted For:
- Olga Lerma
- Submitted By:
- Olga Lerma, URBAN COUNTY
- Department:
- URBAN COUNTY
Information
CAPTION
Requesting authorization to amend construction contract with Venser Contractors, LLC, for reduction of contract days from 150 consecutive calendar days to 120 consecutive calendar days for the Precinct No. 4 Parks, Recreational Facility Improvement project (JR Milo Ponce Park).
BACKGROUND
Contract was approved on September 26, 2017 (AI-61729) with Venser Contractors, LLC. Project consists of improvements JR Milo Ponce Park. Change is requested as recommended by Halff Associates, Project Engineers.
Contractor: VENSER CONTRACTORS, LLC
Construction 120 Consecutive Calendar Days
Period:
Contractor: VENSER CONTRACTORS, LLC
Construction 120 Consecutive Calendar Days
Period:
Fiscal Impact
- CALENDAR YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
No Fiscal Impact - Reduction in contract days.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 09/28/2017 01:57 PM |
| Final Approval | Monica Salinas | 09/29/2017 05:12 PM |
- Form Started By:
- olerma
- Started On:
- 09/28/2017 09:13 AM
- Final Approval Date:
- 09/29/2017