AI- 62136
Purchasing Department   12.A.
CC CONSENT
Prct. 2
Meeting Date:
10/24/2017
Submitted For:
Erika Zamora
Submitted By:
Erika Zamora, COMM. PCT. #2
Department:
COMM. PCT. #2

Information

CAPTION

Ratification of fully executed Change Order No. 4 in connection with contract No. C-16-281-11-15 -Hidalgo County Precinct #2 -YUMA AVENUE EXTENSION PROJECT(from McColl Rd to 0.16 miles east of McColl Rd) as recommended by project inspector, Eugene Palacios and subject to compliance with HB1295 when and if applicable.

BACKGROUND

Request for adjustment of storm manhole. Increase in the amount of $1,800.00.

Fiscal Impact

CALENDAR YEAR:
2017
ACCT. #:
7-1200-431-00-122-126-0-841
FUNDS AVAILABLE Y/N?:
Y/Pending
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Funding pending approval of AI#62137 CC 10/24/17.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 10/17/2017 09:40 PM
Budget and Management Veronica Ortiz 10/19/2017 02:47 PM
Final Approval Monica Salinas 10/20/2017 05:24 PM
Form Started By:
Erika Zamora
Started On:
10/16/2017 04:08 PM
Final Approval Date:
10/20/2017