CAPTION
2013 Bonds Budget 300-J-09 Project Pct.4 Approval to issue payment on the following item: Invoice No. PP11-16-2017 in the amount of $155,024.99 from Hidalgo County Precinct No. 4 for reimbursement of labor, machine hours and fuel related to the construction of the J-09 Project (Pay Periods 11 through 16 of 2017).
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 10/20/2017 05:19 PM |
- Form Started By: