AI - 62464
5.
DRAINAGE - CONSENT
Meeting Date:
11/14/2017
Submitted For:
Jaime Salazar
Submitted By:
Moises Salazar, DRAINAGE DISTRICT
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of the fully executed Change Order No. 2, reflecting a net increase of $4,995.00 and additional 25 calendar days, in connection with the construction contract No. C-HCDD1-17-018-05-30 - Hidalgo County Drainage District No. 1 "Maintenance Building Electrical Upgrade" as recommended by project engineer, Halff Associates, Inc. and approved by HCDD1 General Manager,  Mr. Raul E. Sesin, P.E., C.F.M., subject to compliance with HB1295.

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Monica Salinas 11/09/2017 04:50 PM
Form Started By:
moysalazar
Started On:
11/07/2017 04:38 PM
Final Approval Date:
11/09/2017