AI- 64853
Purchasing Department 17.B.2.
CC - REGULAR
Prct. 4
- Meeting Date:
- 05/15/2018
- Submitted For:
- Marty Salazar
- Submitted By:
- Heidi Ortiz, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
Acceptance and approval of Change Order No. 2 for (additional work items requested by Hidalgo County Irrigation District #1) with details as identified in CO#2 (attached herein) in connection to agreement # C-17-218-01-16 with Texas Cordia Construction, LLC. for: "10th Street Extension Project".
BACKGROUND
Change Order #2 - $65,641.55
Contract #C-17-218-01-16
CSJ: 0921-02-300
Project engineer - L & G
Contract #C-17-218-01-16
CSJ: 0921-02-300
Project engineer - L & G
Fiscal Impact
- CALENDAR YEAR:
- 2018
- ACCT. #:
- 8-1315-431-00-124-030-0-XXX
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Funds available as of 5/11/18TXDOT Participation 96.6% - $63,409.74
Local Participation 3.4% - $2,231.81
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | dbetancourt | 05/10/2018 02:45 PM |
| Budget and Management | Veronica Ortiz | 05/10/2018 02:55 PM |
| Merlen P. Munoz | mmunoz | 05/11/2018 09:43 AM |
| Final Approval | Monica Salinas | 05/11/2018 05:13 PM |