CAPTION
Requesting approval to re-authorize Urban County Program Director to approve certain Change Orders on Urban County Projects.
BACKGROUND
The County of Hidalgo Procurement Procedures, in Section III, No. F (B), permits as follows:
“If a change order involves an increase or decrease in cost of $50,000 or less, the commissioners’ court may grant general authority to an employee to approve change orders. However, the original price may not be increased by more than 25% unless the Change order is necessary to comply with a federal or state statue, rule, regulation, or judicial decision enacted, adopted, or rendered after the contract was made.
The original contract price may not be decreased by 18 percent or more without the consent of the contractor.”
The Urban County Program is requesting that such a Grant of General Authority be made to Director Diana R. Serna, under the conditions listed above, and for Change Orders requesting additional time for completion. This would help to speed up project spending and completion, while Commissioners’ Court would still retain responsibility for any proposed major changes.
“If a change order involves an increase or decrease in cost of $50,000 or less, the commissioners’ court may grant general authority to an employee to approve change orders. However, the original price may not be increased by more than 25% unless the Change order is necessary to comply with a federal or state statue, rule, regulation, or judicial decision enacted, adopted, or rendered after the contract was made.
The original contract price may not be decreased by 18 percent or more without the consent of the contractor.”
The Urban County Program is requesting that such a Grant of General Authority be made to Director Diana R. Serna, under the conditions listed above, and for Change Orders requesting additional time for completion. This would help to speed up project spending and completion, while Commissioners’ Court would still retain responsibility for any proposed major changes.
Fiscal Impact
Attachments
No file(s) attached.
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Veronica Ortiz | 06/29/2018 11:39 AM |
| Final Approval | Monica Salinas | 06/29/2018 06:00 PM |
- Form Started By:
- olerma
- Started On:
- 06/29/2018 08:55 AM
- Final Approval Date:
- 06/29/2018