CAPTION
Requesting approval of Change Order No. 4 reflecting a decrease in the amount of -$35,477.25 and fifty(50) additional calendar days, in connection with contract No. C-HCDD1-18-002-05-22 -Hidalgo County Drainage District No. 1 "New Administration Building" with Bullard Construction, Inc., as recommended by project engineer Halff Associates, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM.
BACKGROUND
HB1295 form has been submitted.
Fiscal Impact