AI - 70136
5.D.
DRAINAGE - CONSENT
- Meeting Date:
- 05/07/2019
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No.1 reflecting an increase of fifteen (15) additional construction calendar days, in connection with contract No. C-HCDD1-18-049-09-25 -Hidalgo County Drainage District No. 1 "Drainage Improvements Project -FM 495 Drain Control Structure and Donna North Lateral Control Structure", awarded to Venser Contractors. LLC, as recommended by project engineer Noe Saldivar, P.E., and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM. (subject to compliance to HB1295)