Skip to main content

AgendaQuick™

View Agenda Item

AI- 70727
Purchasing Department   28.F.2.
CC AGENDA SPECIAL MTG
IT Department
Meeting Date:
07/01/2019
Submitted For:
Marty Salazar
Submitted By:
Elena Gomez, PURCHASING DEPT.
Department:
PURCHASING DEPT.

Information

CAPTION

A. Acceptance and approval of Work Authorization No. 1 (estimated cost of $1,175.00) as submitted by the project engineer, Halff Associates Inc. to provide reimbursable thru contract #C-18-142-05-08.
B. Approval of Change Order #2 from Noble  Texas Builders [with no cost impact] reflecting an extension of the construction to be increased an additional 56 days due to delay in County [IT Dept.]  not receiving ordered equipment Department in connection with the renovation of the Network Operations Center including authority for County Judge or CC member to execute document. 

BACKGROUND


Fiscal Impact

CALENDAR YEAR:
2019
ACCT. #:
9-1100-415-00-200-002-00-430
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

As per E. Kirby Fiscal Impact is addressed through account # 9-1100-415-00-200-002-00-430

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 06/21/2019 02:06 PM
Budget and Management Veronica Ortiz 06/24/2019 09:59 AM
Final Approval Monica Salinas 06/28/2019 08:04 AM
Form Started By:
egomez
Started On:
06/05/2019 11:28 AM
Final Approval Date:
06/28/2019