CAPTION
Requesting approval of Change Order No. 1 in connection with Contract No. C-17-324-07-17 and GMP Amendment No. 1 with Erickson Construction, LLC for the Pct 2 Las Milpas Park Youth Facility Project as recommended by project engineer B2Z Engineering, LLC, and subject to compliance with HB1295 when and if applicable.
BACKGROUND
Change Order No. 1 is for a time extension for rain days and permit required by Hidalgo County Irrigation District No. 2.
No fiscal impact.
No fiscal impact.
Fiscal Impact
- CALENDAR YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
No fiscal impact at this time.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Monica Salinas | 08/09/2019 06:02 PM |
- Form Started By:
- Erika Zamora
- Started On:
- 08/09/2019 04:46 PM
- Final Approval Date:
- 08/09/2019