AI- 72994
Purchasing Department 8.H.
CC CONSENT AGENDA SPECIAL MTG
Prct. 4
- Meeting Date:
- 11/05/2019
- Submitted For:
- Nick Perez
- Submitted By:
- Nick Perez, COMM. PCT. #4
- Department:
- COMM. PCT. #4
Information
CAPTION
Requesting approval of the following items for the Pct.4 10th St Extension Project, as submitted by contractor, Texas Cordia Construction, LLC and as reviewed by project engineer, Ricardo Gallaga, P.E. through contract C-12-126-10-16:
1. Acceptance of Substantial Completion, reflecting the date of June 17, 2019;
2. Acceptance of Certificate of Construction Completion, reflecting the date of August 14, 2019;
3. Application for payment No. 21 (Final & Retainage) in the amount of $476,834.85.
1. Acceptance of Substantial Completion, reflecting the date of June 17, 2019;
2. Acceptance of Certificate of Construction Completion, reflecting the date of August 14, 2019;
3. Application for payment No. 21 (Final & Retainage) in the amount of $476,834.85.
BACKGROUND
AI-72997 approval of CO#6.
Fiscal Impact
- CALENDAR YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Funda available see P.O. 774917 county responsible for 3.4% of total project costs.Attachments
- Certificate of Construction Completion
- Contractor Affidavit of Payments of Debts
- Contractor Affidavit of Release of Liens
- Pay App 21 Final
- completion
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 10/30/2019 04:34 PM |
| Budget and Management | Veronica Ortiz | 10/31/2019 08:09 AM |
| Final Approval | Monica Salinas | 11/01/2019 05:33 PM |
- Form Started By:
- Nick Perez
- Started On:
- 10/28/2019 03:52 PM
- Final Approval Date:
- 11/01/2019