AI- 72997
Purchasing Department 20.E.3.
CC REGULAR AGENDA SPECIAL MTG
Prct. 4
- Meeting Date:
- 11/05/2019
- Submitted For:
- Nick Perez
- Submitted By:
- Nick Perez, COMM. PCT. #4
- Department:
- COMM. PCT. #4
Information
CAPTION
TXDOT PCT 4 (1315):
Acceptance and approval of Change Order No. 6 for (adjustment of estimated quantities to actual as-built quantities) with details identified in CO#6 (attached herein) in connection to agreement # C-17-218-01-16 with Texas Cordia Construction, LLC. for "10th Street Extension Project" including authority for County Judge to sign the required document(s).
Acceptance and approval of Change Order No. 6 for (adjustment of estimated quantities to actual as-built quantities) with details identified in CO#6 (attached herein) in connection to agreement # C-17-218-01-16 with Texas Cordia Construction, LLC. for "10th Street Extension Project" including authority for County Judge to sign the required document(s).
BACKGROUND
Request for contract decrease in the amount of $319,690.74 due to adjustment of estimated quantities to actual as-built quantities in connection to the "10th Street Extension Project".
AI-72994 approval of final pay app, retainage, substantial completion, and construction completion.
AI-72994 approval of final pay app, retainage, substantial completion, and construction completion.
Fiscal Impact
- CALENDAR YEAR:
- ACCT. #:
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
Fiscal impact is a net decrease against previous Change Orders.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 10/30/2019 04:45 PM |
| Budget and Management | Veronica Ortiz | 10/31/2019 08:10 AM |
| Final Approval | Monica Salinas | 11/01/2019 05:33 PM |
- Form Started By:
- Nick Perez
- Started On:
- 10/28/2019 04:23 PM
- Final Approval Date:
- 11/01/2019