CAPTION
Ratification of approved and fully executed Change Order No. 4, in connection with the project -"Jackson Drain Improvements", reflecting addition and reduction of line items with no increase in the contract amount, and additional Twenty-six (26) construction calendar days to contract No. C-HCDD1-18-048-09-25, with Castle Enterprises, LLC, as recommended by project engineer: Jose Noe Saldivar, P.E., HCDD1 Engineer IV, and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM (subject to compliance with HB1295).