CAPTION

Approval of Application for Payment No. 7 in the amount of $149,264.00 to Erickson Construction, LLC. for the "Construction Manager at Risk (CMAR) for the Pct 2 Las Milpas Park Youth Facility Project GMP Amendment #2", through Contract# C-17-324-07-17, and as certified for payment by the project engineer, B2Z Engineering, LLC.

BACKGROUND


Fiscal Impact

CALENDAR YEAR:
2020
ACCT. #:
0-1XXX-451-22-122-141-X-730
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:
N

BUDGETARY IMPACT:

Funding available through PO #795831 for Erickson Construction, LLC, in the amount of $1,132,160.24 as of 08/28/20.

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 08/28/2020 02:44 PM
Budget and Management Veronica Ortiz 08/28/2020 02:50 PM
Final Approval Monica Salinas 08/28/2020 05:32 PM
Form Started By:
Lupita Garza
Started On:
08/28/2020 10:56 AM
Final Approval Date:
08/28/2020