AI - 78780
4.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 12/22/2020
- Submitted For:
- Jaime Salazar
- Submitted By:
- Moises Salazar, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of the fully executed Change Order No. 1 reflecting an increase in the amount of $20,096.10 , and sixty (60) additional construction calendar days, in connection with contract No. C-HCDD1-20-021-06-23 -"Las Milpas -Hidalgo Park Estates" with Mor-Wil, LLC, as recommended by project manager, Jose Noe Saldivar, P.E., HCDD1 Engineer IV, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM.
BACKGROUND
Compliance with HB1295 has been met.
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 12/18/2020 03:04 PM |
- Form Started By:
- moysalazar
- Started On:
- 12/15/2020 04:49 PM
- Final Approval Date:
- 12/18/2020