CAPTION
A. Requesting approval of Work Authorization No. 3 (with an estimated cost of $1,511,000.00) as submitted by the project engineer, L & G Engineering, to provide engineering services through Contract #C-18-195-07-31 for the "Mile 6 Project (M14 1/2 to SH 107) in Pct.1.
B. Pursuant to Article 14 of the current agreement C-18-195-07-31, request by L&G Engineering to engage the following subcontractor: Ergonomic Transportation Solutions, Inc.
B. Pursuant to Article 14 of the current agreement C-18-195-07-31, request by L&G Engineering to engage the following subcontractor: Ergonomic Transportation Solutions, Inc.
BACKGROUND
Project# 2021-222
L& G Engineering:
L& G Engineering:
- PS&E Development Roadway and Irrigation Structures
- Signal and Temporary Signal Design
- Geotechnical and Pavement Design
- Permitted Utilities Coordination
- Set of plans for submittal to TxDOT
- Design plans, specifications and cost estimates for flashing beacons, temporary and permanent traffic signals.
Fiscal Impact
- CALENDAR YEAR:
- 2021
- ACCT. #:
- 1-1315-431-00-121-039-2-710
- FUNDS AVAILABLE Y/N?:
- Y/pend
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
pending rollover from FY20.Attachments
- Work Authorization No.3
- Subcontracting Notice
- 1295 Form
- 2-16-21 WA No.3 to C-18-195-07-31 btwn L&G Consulting Engineers & HC - To provide Engineering Services for Mi 6 Project (Mi14.5 - SH 107)
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | msalazar | 02/12/2021 11:45 AM |
| Budget and Management | Veronica Ortiz | 02/12/2021 12:57 PM |
| Final Approval | Monica Salinas | 02/12/2021 04:56 PM |
- Form Started By:
- Hector Garcia
- Started On:
- 02/08/2021 04:09 PM
- Final Approval Date:
- 02/12/2021