CAPTION
Ratification of the fully executed Change Order No. 1 reflecting an increase in the amount of $33,371.93, and additional Twenty (20) construction calendar days, in connection with the Contract C-HCDD1-20-001-02-11 -"Hidalgo Drain & Dicker Road Box Culvert Crossing" with Mor-Wil, LLC, as recommended by Project Engineer, Jose Noe Saldivar, P.E., HCDD1 Engineer IV and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.
BACKGROUND
Compliance to HB1295 has been met.