Discussion, consideration and action on Amendment Nos. 11 & 14 [as drafted by Hon. J. Hawkins, Porter Hedges] between Hidalgo County and Architect, HDR Architecture, Inc., [C-16-141-10-31] to include the following Scopes of Work in connection with the "Construction of the New Hidalgo County Courthouse" Project: 

A. Requesting approval of Amendment No.11:
 
Amendment No.11 - [Phase 2]
Description Cost
Comprehensive Site Demolition, Site Design & Procurement Scope
* Including Sub-Consultants and Expenses
Task 1 - Design (Assumed to be 4 Months)
Task 2 - Procurement (Assumed to be 6 Months)

$346,787.00
Construction Contract Administration Scope [CCA]
* Including Sub-Consultants and Expenses
Task 3 - CCA (Assumed to be 10 Months)

Demo Work Portion - (Assumed to be 4 Months)



Construction Site Work - (Assumed to be 6 Months)





$29,407.00
 (Monthly Fee)

$63,598.00
 (Monthly Fee)
TOTAL FOR AMENDMENT 11 $846,003.00

B. Requesting approval of Amendment No.14:
 
Amendment No.14 - Mechanical Screen Wall
Redesign of Mechanical Screen Wall
*Re-engineered the design for easier transport of the Mechanical Screen Wall up to the roof, as there is no crane on site now.
Redesign (Assumed to be 3 weeks)
$29,350.00

C. Requesting authority for County Judge and/or (if applicable) Owner's Designated Representative to sign required documents.

BACKGROUND


Fiscal Impact

CALENDAR YEAR:
2021
ACCT. #:
1-1XXX-419-40-125-035-0-XXX
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:


CALENDAR YEAR:
2021
ACCT. #:
1-1100-419-40-125-035-0-730
FUNDS AVAILABLE Y/N?:
Y
MATCHING FUNDS Y/N?:

BUDGETARY IMPACT:

Attachments

Form Review

Inbox Reviewed By Date
Purchasing / Internal msalazar 06/11/2021 05:44 PM
Final Approval Monica Salinas 06/12/2021 08:37 AM
Form Started By:
Hector Garcia
Started On:
06/10/2021 03:47 PM
Final Approval Date: