AI- 82196
Purchasing Department 23.B.1.
CC REGULAR AGENDA SPECIAL MTG
Executive Office
- Meeting Date:
- 09/07/2021
- Submitted For:
- Marty Salazar
- Submitted By:
- Jaime Cortez, PURCHASING DEPT.
- Department:
- PURCHASING DEPT.
Information
CAPTION
Requesting acceptance and approval of final negotiated AIA Document to award the #1 ranked firm ECON in the amount of $4,026,100.00 as the CSP General Contractor for the Pct 4 - New Justice Center Project.
BACKGROUND
Proj. No.: 21-229
Architect: ROFA
Construction Manager: B2Z
ECON selected as #1 ranked firm via AI-81532 (7/13/2021)
Agreement A101-2017 & A201-2017
Architect: ROFA
Construction Manager: B2Z
ECON selected as #1 ranked firm via AI-81532 (7/13/2021)
Agreement A101-2017 & A201-2017
Fiscal Impact
- CALENDAR YEAR:
- 2021
- ACCT. #:
- 1-1353-412-00-220-054-0-730
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
Difference in funding has been authorized by court and is pending the sale of Certificates of Obligation, Series 2021.Attachments
- 1295
- A201-2017 Final
- Legal Review
- A101-2017 Final
- Addenda 1 thru 8
- Exhibit A - RFCSP Procurement Packet
- Exhibit B - ECON Bid Response
- Exhibit D - Specifications
- Exhibit E - Contract Drawings
- Exhibit F - Notice to Proceed
- AIA Executed
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Dina Trevino | 09/02/2021 03:32 PM |
| Budget and Management | Veronica Ortiz | 09/02/2021 03:50 PM |
| Final Approval | Monica Salinas | 09/03/2021 06:59 PM |
- Form Started By:
- jcortez
- Started On:
- 08/26/2021 03:38 PM
- Final Approval Date:
- 09/03/2021