CAPTION
Ratification of the fully executed Change Order No. 5 reflecting forty-five (45) additional construction calendar days, in connection with Contract No. C-HCDD1-20-026-06-23 - "PD Lateral (Phase 1) -2018 Bond Referendum Project #29" with Mor-Wil, LLC, as recommended by Project Engineer, Izaguirre Engineering Group, LLC, and approved by HCDD1 General Manager, Mr. Raul E. Sesin, P.E., CFM.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Jaime Salazar | 11/12/2021 04:23 PM |
- Form Started By:
- moysalazar
- Started On:
- 11/09/2021 04:54 PM
- Final Approval Date:
- 11/12/2021