AI - 85294
5.B.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 04/05/2022
- Submitted For:
- Jaime Salazar
- Submitted By:
- Enriqueta Zambrano, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No. 9, in connection with the project -"PD Lateral (Phase II)-2018 Bond Referendum Project No. 29", reflecting Eighteen (18) additional construction calendar days to Contract No. C-HCDD1-20-029-06-23, with Mor-Will, LLC, as recommended by Izaguirre Engineering Group, LLC., and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.
BACKGROUND
Compliance with HB-1295
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 04/01/2022 04:32 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 03/31/2022 08:41 AM
- Final Approval Date:
- 04/01/2022