AI - 85405
4.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 04/19/2022
- Submitted For:
- Jaime Salazar
- Submitted By:
- Enriqueta Zambrano, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No. 8, in connection with the project -"PD Lateral (Phase I)-2018 Bond Referendum Project No. 29", reflecting Fourty-Five (45) additional construction calendar days to Contract No. C-HCDD1-20-026-06-23, with Mor-Wil, LLC as recommended by Izaguirre Engineering Group, LLC., and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM
BACKGROUND
Reason for Change Order:
1. 15 Days to Adverse Weather -Rainy days
2. 30 Days due to revision on material and easement verifications
Compliance with HB-1295
1. 15 Days to Adverse Weather -Rainy days
2. 30 Days due to revision on material and easement verifications
Compliance with HB-1295
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 04/14/2022 04:48 PM |
- Form Started By:
- Enriqueta Zambrano
- Started On:
- 04/11/2022 04:51 PM
- Final Approval Date:
- 04/14/2022