DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 11/15/2022
- Submitted For:
- Jaime Salazar
- Submitted By:
- Enriqueta Zambrano, DRAINAGE DISTRICT
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No. 4, in connection with the project "Mile 9 N. & FM 1015 Package 2 -2018 Bond Referendum Project No. 24’’, reflecting an increase of $21,572.54 and Forty-Five (45) additional construction calendar days to Contract No. C-HCDD1-20-065-01-19, with Mor-Wil, LLC, as recommended by Project Engineer, Asst. District General Manager, Yvette Barrera, PE, CFM.