Ratification of approved and fully executed Change Order No. 2, in connection with the project "Faysville Drain Improvements -2018 Bond Referendum Project No. 11B’’, reflecting an increase of $21,025.20 and Eighty (80) additional construction calendar days to Contract No. C-HCDD1-21-048-11-30, with RDH Site and Concrete, LLC, as recommended by Project Engineer, TEDSI Infrastructure Group.