AI - 92718
3.A.
DD-CONSENT AGENDA SPECIAL MTG
Meeting Date:
10/03/2023
Submitted For:
Omar Anzaldua Jr.
Submitted By:
Enriqueta Zambrano
Department:
DRAINAGE DISTRICT

Information

CAPTION

Ratification of approved and fully executed Change Order No. 1, for the project "South Lateral Drain Improvements Phase I'', reflecting an increase of thirty-five (35) additional construction calendar days to Contract No. C-HCDD1-20-009-R-04-04, with Saenz Brothers Construction, LLC., as recommended by Project Engineer, Asst. District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM.

BACKGROUND

 Project completion date as per CO-1: September 7, 2023

Fiscal Impact