CAPTION
Ratification of approved and fully executed Change Order No.1, in connection with the project "4 1/2 Mile Rd & Doffing Rd Drainage Improvements - 2018 Bond Project No. 3’', reflecting additional fourteen (14) construction calendar days and an increase amount of $15,040.00 to Contract No. C-HCDD1-23-048-09-26, with The 5125 Company, as recommended by Project Engineer, CSJ Group.
BACKGROUND
Completion Date per Change Order 1: March 30, 2024
Fiscal Impact