1. PIPELINE PERMITS
a. Applicant: RGV Land Development LLC.
Legal Description: Lot 13 out of Blk. 63, Lot 4 out of Blk. 64 Capisallo District Subdivision; Proposed Los Prados Ph. 1 Subdivision (Mile 9 North Road & Baseline Road) (Pct.1)
Location of Pipeline or Utilities: Existing sanitary sewer manhole north of Mile 9 North Road.
Proposed improvement within Right-of-Way: A 12-inch PVC sewer line will be installed to connect to the existing sewer manhole north of Mile 9 North Road. The sewer line will run west for about 88.33 feet, then turn south and cross Mile 9 North Road via an open cut. After that, it will turn west again and continue for approximately 1/4 mile along the south side of Mile 9 North Road within a 15-foot NAWSC exclusive easement bore crossing FM 491. The sewer line will then continue west for 50 feet to a proposed sewer manhole, turning north and crossing mile 9 North Road via an open cut to reach another sewer
b. Applicant: North Alamo Water Supply Corporation
Legal Description: 26.82 acres out of lot 12 Blk. 99 Campacuas Addition Subdivision of Llano Grande Grant; Proposed: San Jacinto Estates No. 15 Subdivision (Mile 11 North Road & Mile 2 West Road) (Pct.1)
Proposed improvement within Right-of-Way: This proposal is to open up the section where the existing water service lines are, disconnect them from the existing 6" water line, and extend them east to connect to the new 8" water line installed by the San Jacinto Estates No.15 Subdivision Development.
a. Applicant: RGV Land Development LLC.
Legal Description: Lot 13 out of Blk. 63, Lot 4 out of Blk. 64 Capisallo District Subdivision; Proposed Los Prados Ph. 1 Subdivision (Mile 9 North Road & Baseline Road) (Pct.1)
Location of Pipeline or Utilities: Existing sanitary sewer manhole north of Mile 9 North Road.
Proposed improvement within Right-of-Way: A 12-inch PVC sewer line will be installed to connect to the existing sewer manhole north of Mile 9 North Road. The sewer line will run west for about 88.33 feet, then turn south and cross Mile 9 North Road via an open cut. After that, it will turn west again and continue for approximately 1/4 mile along the south side of Mile 9 North Road within a 15-foot NAWSC exclusive easement bore crossing FM 491. The sewer line will then continue west for 50 feet to a proposed sewer manhole, turning north and crossing mile 9 North Road via an open cut to reach another sewer
b. Applicant: North Alamo Water Supply Corporation
Legal Description: 26.82 acres out of lot 12 Blk. 99 Campacuas Addition Subdivision of Llano Grande Grant; Proposed: San Jacinto Estates No. 15 Subdivision (Mile 11 North Road & Mile 2 West Road) (Pct.1)
Proposed improvement within Right-of-Way: This proposal is to open up the section where the existing water service lines are, disconnect them from the existing 6" water line, and extend them east to connect to the new 8" water line installed by the San Jacinto Estates No.15 Subdivision Development.
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Budget and Management | Melannie Rivera | 03/14/2024 09:41 AM |
| Final Approval | Monica Salinas | 03/15/2024 05:24 PM |
- Form Started By:
- Flor Castillo
- Started On:
- 03/13/2024 05:03 PM
- Final Approval Date:
- 03/15/2024