AI - 94776
3.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 04/02/2024
- Submitted For:
- Yvette Barrera
- Submitted By:
- Justin Silva
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No. 2 reflecting an increase in the amount of $25,498.00 and twenty-eight (28) additional calendar days, for the project "Jackson Rd Drain Ph II -2018 Bond Referendum Project No. 16'', (C-HCDD1-23-026-06-30), with RDH Site & Concrete, LLC, as recommended by Project Engineer, Quintanilla Headley and Associates and approved by HCDD1 General Manager Raul E. Sesin, PE, CFM (Subject to compliance with HB-1295).
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 03/28/2024 03:10 PM |
- Form Started By:
- Justin Silva
- Started On:
- 03/28/2024 09:34 AM
- Final Approval Date:
- 03/28/2024