CAPTION

Ratification of approved and fully executed Change Order No. 8, reflecting an increase in the amount of  $38,874.44 and 30 additional days, for the project "Mid-Valley Airport Ditch 18B Drainage Improvements - 2018 Bond Referendum Project No. 19’', Contract No. C-HCDD1-22-020-05-31, with Mor-Wil, LLC, as recommended by Project Engineer, B2Z Engineering, LLC., and approved by HCDD1 General Manager, Raul E. Sesin, P.E., CFM.