CAPTION
Ratification of approved and fully executed Change Order No.3, reflecting (230) additional calendar days for the project ''Highway 281 & FM 88 -2018 Bond Referendum Project No. 14'', Contract No. (C-HCDD1-22-019-07-12), with Go Underground, LLC, as recommended by Project Manager, B2Z Engineering, LLC and approved by District General Manager, Raul E. Sesin, PE, CFM.