Requesting acceptance and approval of Change Order No. 2 from IOC Company, LLC, for the "Liberty Blvd. Project (US 83 to Mile 3 Rd.)" (C-24-0148-05-29-10) to reflect the modifications to the irrigation crossing and increase the contract price by $72,730.70, as recommended by the Construction Manager firm SAMES, Inc.
BACKGROUND
In coordination with the Hidalgo County Irrigation District No. 16 (HCID No.16), modifications have been requested to the irrigation crossing located within HCID No. 16 right-of-way in order to meet the requirements for their final approval.
Fiscal Impact
- CALENDAR YEAR:
- 2025
- ACCT. #:
- 5-1315-431-00-123-128-0-841
- FUNDS AVAILABLE Y/N?:
- MATCHING FUNDS Y/N?:
BUDGETARY IMPACT:
As per Precinct 3, the County's responsibility is 1.8%.Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Ignacio Amezcua | 05/09/2025 10:24 AM |
| Budget and Management | Veronica Ortiz | 05/09/2025 10:31 AM |
| Final Approval | Monica Salinas | 05/09/2025 05:51 PM |
- Form Started By:
- Cassandra Carr
- Started On:
- 04/28/2025 03:47 PM
- Final Approval Date:
- 05/09/2025