AI - 100297
3.A.
DD-CONSENT AGENDA SPECIAL MTG
- Meeting Date:
- 08/05/2025
- Submitted For:
- Omar Anzaldua Jr.
- Submitted By:
- Enriqueta Zambrano
- Department:
- DRAINAGE DISTRICT
Information
CAPTION
Ratification of approved and fully executed Change Order No.4, reflecting 50 additional calendar days for the project ''South Main Drain Channel Improvements Project Phase I -2023 Bond Referendum Project No. 3'', Contract No. (C-HCDD1-23-053-10-31), with RG Enterprises, LLC dba G&G Contractors, as recommended by Project Engineer, Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM and approved by District General Manager, Raul E. Sesin, PE, CFM.
BACKGROUND
Project completion date as per change order 4 -October 14, 2025
Fiscal Impact
Attachments