CAPTION
Anaquitas Phase 2 - Budget 508
1. Approval of Application for Payment No. 3 in the amount of $240,120.00 from Gonzalez Engineering pertaining to Construction Contract C-HCDD1-25-006-02-18 Anaquitas Phase 2. Project Engineer L&G Engineering PO#650692
Hidalgo Drain - Budget 513
2. Approval of Application for Payment No. 6 in the amount of $178,194.60 from RDH Site & Concrete pertaining to Construction Contract C-HCDD1-24-034-08-06 Hidalgo Drain. Project Engineer SAMES Engineering PO#649905
Southwest Weslaco - Budget 535
3. Approval of Application for Payment No. 5 in the amount of $228,806.60 from Mor-Wil, LLC pertaining to Construction Contract C-HCDD124-055-11-12 Southwest Weslaco. Project Engineer S2 Engineering PO#650124
1. Approval of Application for Payment No. 3 in the amount of $240,120.00 from Gonzalez Engineering pertaining to Construction Contract C-HCDD1-25-006-02-18 Anaquitas Phase 2. Project Engineer L&G Engineering PO#650692
Hidalgo Drain - Budget 513
2. Approval of Application for Payment No. 6 in the amount of $178,194.60 from RDH Site & Concrete pertaining to Construction Contract C-HCDD1-24-034-08-06 Hidalgo Drain. Project Engineer SAMES Engineering PO#649905
Southwest Weslaco - Budget 535
3. Approval of Application for Payment No. 5 in the amount of $228,806.60 from Mor-Wil, LLC pertaining to Construction Contract C-HCDD124-055-11-12 Southwest Weslaco. Project Engineer S2 Engineering PO#650124
BACKGROUND
Fiscal Impact
Attachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Final Approval | Nora Cavazos | 10/22/2025 04:28 PM |
- Form Started By:
- Alvaro Chuc
- Started On:
- 10/21/2025 03:20 PM
- Final Approval Date:
- 10/22/2025