CAPTION
Ratification of the approved and fully executed Change Order No.1, reflecting an increase in the amount of $808.21 and 120 additional calendar days for the project 'Alamo Expressway Drain Phase II -2023 Bond Referendum Project No. 21'', Contract No. (C-HCDD1-24-047-09-17), with 3E Logistics of TX, LLC., as recommended by Project Engineer, GDJ Engineering LLC and approved by District General Manager, Raul E. Sesin, PE, CFM.