Skip to main content

AgendaQuick™

View Agenda Item

AI - 101273
7.C.
DD-REGULAR AGENDA SPECIAL MTG
Meeting Date:
10/28/2025
Submitted By:
Alvaro Chuc
Department:
DRAINAGE DISTRICT

Information

CAPTION

Anaquitas Phase 2 - Budget 508
1. Approval of Application for Payment No. 3 in the amount of $240,120.00 from Gonzalez Engineering pertaining to Construction Contract C-HCDD1-25-006-02-18 Anaquitas Phase 2. Project Engineer L&G Engineering PO#650692

Hidalgo Drain - Budget 513
2. Approval of Application for Payment No. 6 in the amount of $178,194.60 from RDH Site & Concrete pertaining to Construction Contract C-HCDD1-24-034-08-06 Hidalgo Drain. Project Engineer SAMES Engineering PO#649905

Southwest Weslaco - Budget 535
3. Approval of Application for Payment No. 5 in the amount of $228,806.60 from Mor-Wil, LLC pertaining to Construction Contract C-HCDD124-055-11-12 Southwest Weslaco. Project Engineer S2 Engineering PO#650124

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Nora Cavazos 10/22/2025 04:28 PM
Form Started By:
Alvaro Chuc
Started On:
10/21/2025 03:20 PM
Final Approval Date:
10/22/2025