CAPTION
Requesting approval of Change Order No.2, reflecting an increase in the amount of $76,725.00 and 60 additional calendar days for the project ''Mission-McAllen Drain Phase 2 -2023 Bond Referendum Project No. 12'', Contract No. C-HCDD1-24-057-10-29, with Synergy Development & Construction, LLC, as recommended by Project Engineer, Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM.
BACKGROUND
End Date for Chage Order 2: March 10, 2026