CAPTION

Anaquitas Phase 2 - Budget 508
1. Approval and acceptance of Certificate of Substantial Completion and Certificate of Construction Completion from Gonzalez Engineering & Management pertaining to Construction Contract C-HCDD1-25-006-02-18 Anaquitas Phase 2-Project Engineer L&G Engineering PO#650692
2. Approval of Application for Payment No. 5 Retainage in the amount of $79,605.18 and $332.33 in interest from Gonzalez Engineering & Management pertaining to Construction Contract C-HCDD1-25-006-02-18 Anaquitas Phase 2-Project Engineer L&G Engineering PO#650692

BACKGROUND


Fiscal Impact

Attachments

Form Review

Inbox Reviewed By Date
Final Approval Jaime Salazar 02/25/2026 04:13 PM
Form Started By:
Alvaro Chuc
Started On:
02/24/2026 01:08 PM
Final Approval Date:
02/25/2026