CAPTION

La Villa Edcouch Elsa Phase 2 - Budget 708
1. Approval of Application for Payment No. 3 in the amount of $224,502.44 from Construx Enterprises pertaining to Construction Contract C-HCDD1-25-036-07-22. Project Engineer S2 Engineering PO#651335
West Main Drain 3 Phase 1 - Budget 714
2. Approval of Application for Payment No. 8 in the amount of $113,023.16 from E-Con Group pertaining to Construction Contract C-HCDD1-24-061-12-17. Project Engineer L&G Engineering PO#650460

BACKGROUND


Fiscal Impact