Requesting approval of Change Order No. 2, reflecting an increase in the amount of $96,650.00 and 90 additional construction calendar days for the project "La Villa Edcouch Elsa Phase II - USIBWC Structure 603AL - 2023 Bond Project No. 8.2", Contract No. C-HCDD1-25-036-07-22, with Construx Enterprises, LLC, as recommended by Project Engineer, Assistant District General Manager, Omar Anzaldua Jr., PE, CFM, PMP, CCM