AI- 103215
Purchasing Department 15.C.3.
CC CONSENT AGENDA REGULAR MTG
Prct. 2
- Meeting Date:
- 04/28/2026
- Submitted For:
- Eddie Cantu
- Submitted By:
- Lupita Garza
- Department:
- COMM. PCT. #2
CAPTION
Requesting approval of Change Order No. 1 (C-25-0063-04-01) with RBM Contractors, LLC for the Hidalgo County Precinct 2 — Recreational Trails Connectivity Project - Mission Segment 2, as recommended by project manager, Stanley Ramos, with authority for Commissioner Eduardo "Eddie" Cantu to sign the approved change order. (ARPA-21-122-040)
BACKGROUND
Requesting 28 credit days due to weather and holidays. Requesting an additional 60 days due to Design Modifications. Total of 88 additional working calendar days. Resulting in a new contract expiration date of 06/17/26. No fiscal impact.
Fiscal Impact
- CALENDAR YEAR:
- 2026
- ACCT. #:
- 1290-52-115-000-0000-507400
- FUNDS AVAILABLE Y/N?:
- Y
- MATCHING FUNDS Y/N?:
- N
BUDGETARY IMPACT:
N/AAttachments
Form Review
| Inbox | Reviewed By | Date |
|---|---|---|
| Purchasing / Internal | Ignacio Amezcua | 04/21/2026 10:24 AM |
| Budget and Management | Veronica Ortiz | 04/21/2026 10:26 AM |
| Final Approval | Monica Salinas | 04/22/2026 04:53 PM |
- Form Started By:
- Lupita Garza
- Started On:
- 04/21/2026 09:39 AM
- Final Approval Date: